Figures refresh every night. [How each figure is worked out](/methodology/).





In March 2026 the Government Major Projects Portfolio held **189 projects**. Of the 81 with an independent delivery confidence rating, **24 were rated red**, 51 amber and 6 green. Red is the lowest of the three ratings; the authority defines each in its annual report. The projects with a published whole-life cost total £437.7bn (2024-25 real prices, as the file states). Source: NISTA Major Projects Annual Report 2025-26.






## Key figures



- 189Projects in the portfolio

▼
March 2026
- 24Rated red by the independent assessors

▲
March 2026
- 30%Of the 81 with an independent rating, the share rated red

23% in March 2025
March 2026
- £437.7bnWhole-life cost of the 132 projects with a published figure

In 2024-25 real prices: not comparable with March 2025
March 2026







## What is the short version?



- **The scale has changed:** it had five points before March 2022, and from the 2024-25 data each project carries either the independent rating or the department’s own, so fewer have an independent one.
- **Costs cover only the projects that publish one:** 132 of 189 in March 2026. Some ratings and costs are withheld under the Freedom of Information Act.
- **Totals are not comparable across that change:** the March 2026 file gives costs in 2024-25 real prices; earlier files mostly in cash.
- **A rise in a project’s cost is not necessarily an overspend:** a change in scope, in timing or in how costs are counted moves it too.






## How have the ratings changed over time?




**Independent delivery confidence ratings, March 2026**



- ◆ Red

30% 24 of 81
- Amber

63% 51 of 81
- Green

7.4% 6 of 81




Shares of the 81 projects with an independent rating, out of 189 in the portfolio. Red is the lowest of the three ratings.




**Show as a table**





| Item | Share | Detail |
| --- | --- | --- |
| RedDetails | 29.6% | 24 of 81 |
| Detail24 of 81 | | |
| AmberDetails | 63.0% | 51 of 81 |
| Detail51 of 81 | | |
| GreenDetails | 7.4% | 6 of 81 |
| Detail6 of 81 | | |









**Projects by delivery confidence rating, March 2022 to March 2026**


- ◆ Rated red





March 2022: 24 → March 2026: **24**

- Amber





March 2022: 115 → March 2026: **51**

- Green





March 2022: 11 → March 2026: **6**

- Department’s own rating only





March 2022: 68 → March 2026: **91**

- No rating published





March 2022: 14 → March 2026: **17**



Numbers of projects, every panel on the same scale from zero. From the 2024-25 data a project carries either the independent rating or the department’s own, so part of the fall in independent ratings comes from that change.




**Show as a table**





| Data as at | Rated red | Amber | Green | Department’s own rating only | No rating published |
| --- | --- | --- | --- | --- | --- |
| March 2022Details | 24 | 115 | 11 | 68 | 14 |
| Amber115Green11Department’s own rating only68No rating published14 | | | | | |
| March 2023Details | 18 | 88 | 5 | 121 | 12 |
| Amber88Green5Department’s own rating only121No rating published12 | | | | | |
| March 2024Details | 20 | 91 | 4 | 100 | 12 |
| Amber91Green4Department’s own rating only100No rating published12 | | | | | |
| March 2025Details | 20 | 61 | 5 | 110 | 17 |
| Amber61Green5Department’s own rating only110No rating published17 | | | | | |
| March 2026Details | 24 | 51 | 6 | 91 | 17 |
| Amber51Green6Department’s own rating only91No rating published17 | | | | | |










| Data as at | Projects | Rated red | Amber | Green | Department’s own rating only | No rating published | Whole-life cost of projects with a figure |
| --- | --- | --- | --- | --- | --- | --- | --- |
| March 2022Details | 232 | 24 | 115 | 11 | 68 | 14 | £490.6bn188 projects, cash, as each department reported it |
| Rated red24Amber115Green11Department’s own rating only68No rating published14Whole-life cost of projects with a figure£490.6bn188 projects, cash, as each department reported it | | | | | | | |
| March 2023Details | 244 | 18 | 88 | 5 | 121 | 12 | £471.8bn193 projects, cash, as each department reported it |
| Rated red18Amber88Green5Department’s own rating only121No rating published12Whole-life cost of projects with a figure£471.8bn193 projects, cash, as each department reported it | | | | | | | |
| March 2024Details | 227 | 20 | 91 | 4 | 100 | 12 | £448.0bn174 projects, cash, as each department reported it |
| Rated red20Amber91Green4Department’s own rating only100No rating published12Whole-life cost of projects with a figure£448.0bn174 projects, cash, as each department reported it | | | | | | | |
| March 2025Details | 213 | 20 | 61 | 5 | 110 | 17 | £535.6bn148 projects, cash, as the file states |
| Rated red20Amber61Green5Department’s own rating only110No rating published17Whole-life cost of projects with a figure£535.6bn148 projects, cash, as the file states | | | | | | | |
| March 2026Details | 189 | 24 | 51 | 6 | 91 | 17 | £437.7bn132 projects, 2024-25 real prices, as the file states |
| Rated red24Amber51Green6Department’s own rating only91No rating published17Whole-life cost of projects with a figure£437.7bn132 projects, 2024-25 real prices, as the file states | | | | | | | |






**Why the years are not quite like for like**



The independent rating is the Infrastructure and Projects Authority’s delivery confidence assessment, now made by
the National Infrastructure and Service Transformation Authority. From the 2024-25 data a project carries either
that rating or its senior responsible owner’s own rating, not both, so the number with an independent rating has
fallen. Before March 2022 the scale had five points; this table starts when it became red, amber and green. Some
ratings and costs are withheld under the Freedom of Information Act, which is why not every project has a figure.
Costs are not adjusted between years except where the file says so: the March 2026 file gives costs in
2024-25 real prices.




Source: [Infrastructure and Projects Authority, now the National Infrastructure and Service Transformation Authority, Government Major Projects Portfolio data](https://www.gov.uk/government/collections/major-projects-data), March 2022 to March 2026.





## Which projects are in the March 2026 data?




**The ten largest projects by whole-life cost, March 2026**



- 1. NEW HOSPITAL PROGRAMME (DHSC)

£47.5bn
- 2. NORTHERN POWERHOUSE RAIL (DFT)

£45.0bn
- 3. FARMING AND COUNTRYSIDE PROGRAMME (DEFRA)

£25.5bn
- 4. Smart Metering Implementation Programme (DESNZ)

£20.2bn
- 5. EMERGENCY SERVICES MOBILE COMMUNICATIONS (HO)

£18.1bn
- 6. Early Years Childcare Reform Programme (DFE)

£16.2bn
- 7. ASTUTE BOATS 1-7 (MOD)

£14.4bn
- 8. NAVAL SUPPORT INTEGRATED GLOBAL NETWORK (NSIGN) (MOD)

£14.4bn
- 9. Affordable Homes Programme (AHP) (MHCLG)

£12.2bn
- 10. TRANSPENNINE ROUTE UPGRADE (DFT)

£10.7bn





Costs as the file gives them (2024-25 real prices, as the file states). 57 of the 189 projects have no published cost. Every project is in the table below.




**Show as a table**





| Name | Whole-life cost, March 2026 |
| --- | --- |
| 1. NEW HOSPITAL PROGRAMME (DHSC) | £47.5bn |
| 2. NORTHERN POWERHOUSE RAIL (DFT) | £45.0bn |
| 3. FARMING AND COUNTRYSIDE PROGRAMME (DEFRA) | £25.5bn |
| 4. Smart Metering Implementation Programme (DESNZ) | £20.2bn |
| 5. EMERGENCY SERVICES MOBILE COMMUNICATIONS (HO) | £18.1bn |
| 6. Early Years Childcare Reform Programme (DFE) | £16.2bn |
| 7. ASTUTE BOATS 1-7 (MOD) | £14.4bn |
| 8. NAVAL SUPPORT INTEGRATED GLOBAL NETWORK (NSIGN) (MOD) | £14.4bn |
| 9. Affordable Homes Programme (AHP) (MHCLG) | £12.2bn |
| 10. TRANSPENNINE ROUTE UPGRADE (DFT) | £10.7bn |








Search




| Project | Department | Delivery confidence | Whole-life cost, March 2026 | Whole-life cost, March 2025 | Difference |
| --- | --- | --- | --- | --- | --- |
| NEW HOSPITAL PROGRAMMEDetails | DHSC | Amber (independent) | £47.5bn | £60.0bn | −£12.5bn |
| DepartmentDHSCDelivery confidenceAmber (independent)Whole-life cost, March 2025£60.0bnDifference−£12.5bn | | | | | |
| NORTHERN POWERHOUSE RAILDetails | DFT | Amber (independent) | £45.0bn | £30.6bn | +£14.4bn |
| DepartmentDFTDelivery confidenceAmber (independent)Whole-life cost, March 2025£30.6bnDifference+£14.4bn | | | | | |
| FARMING AND COUNTRYSIDE PROGRAMMEDetails | DEFRA | Red (independent) | £25.5bn | £24.9bn | +£620m |
| DepartmentDEFRADelivery confidenceRed (independent)Whole-life cost, March 2025£24.9bnDifference+£620m | | | | | |
| Smart Metering Implementation ProgrammeDetails | DESNZ | Amber (department’s own) | £20.2bn | £20.2bn | −£0m |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£20.2bnDifference−£0m | | | | | |
| EMERGENCY SERVICES MOBILE COMMUNICATIONSDetails | HO | Amber (independent) | £18.1bn | £19.2bn | −£1.0bn |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£19.2bnDifference−£1.0bn | | | | | |
| Early Years Childcare Reform ProgrammeDetails | DFE | Green (independent) | £16.2bn | £15.1bn | +£1.1bn |
| DepartmentDFEDelivery confidenceGreen (independent)Whole-life cost, March 2025£15.1bnDifference+£1.1bn | | | | | |
| ASTUTE BOATS 1-7Details | MOD | Amber (department’s own) | £14.4bn | £11.6bn | +£2.9bn |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£11.6bnDifference+£2.9bn | | | | | |
| NAVAL SUPPORT INTEGRATED GLOBAL NETWORK (NSIGN)Details | MOD | Amber (department’s own) | £14.4bn | £20.3bn | −£5.9bn |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£20.3bnDifference−£5.9bn | | | | | |
| Affordable Homes Programme (AHP)Details | MHCLG | Amber (independent) | £12.2bn | £12.3bn | −£107m |
| DepartmentMHCLGDelivery confidenceAmber (independent)Whole-life cost, March 2025£12.3bnDifference−£107m | | | | | |
| TRANSPENNINE ROUTE UPGRADEDetails | DFT | Amber (department’s own) | £10.7bn | £11.1bn | −£397m |
| DepartmentDFTDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£11.1bnDifference−£397m | | | | | |
| LOWER THAMES CROSSINGDetails | DFT | Amber (independent) | £9.9bn | £8.9bn | +£950m |
| DepartmentDFTDelivery confidenceAmber (independent)Whole-life cost, March 2025£8.9bnDifference+£950m | | | | | |
| Remediation PortfolioDetails | MHCLG | Red (independent) | £9.7bn | £9.9bn | −£188m |
| DepartmentMHCLGDelivery confidenceRed (independent)Whole-life cost, March 2025£9.9bnDifference−£188m | | | | | |
| Hydrogen Allocation Round 2 (HAR2)Details | DESNZ | Red (independent) | £9.4bn | Not in the portfolio | — |
| DepartmentDESNZDelivery confidenceRed (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| ARMOURED CAVALRY 2025Details | MOD | Red (independent) | £8.9bn | £7.5bn | +£1.4bn |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025£7.5bnDifference+£1.4bn | | | | | |
| CORE PRODUCTION CAPABILITYDetails | MOD | Amber (independent) | £7.8bn | £5.9bn | +£1.9bn |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£5.9bnDifference+£1.9bn | | | | | |
| LAND ENVIRONMENT TACTICAL COMMUNICATION AND INFORMATION SYSTEMSDetails | MOD | Amber (independent) | £7.7bn | £8.2bn | −£474m |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£8.2bnDifference−£474m | | | | | |
| DEFENCE ESTATE OPTIMISATIONDetails | MOD | Amber (department’s own) | £5.9bn | £6.4bn | −£427m |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£6.4bnDifference−£427m | | | | | |
| Project GigabitDetails | DSIT | Amber (department’s own) | £5.2bn | £5.4bn | −£189m |
| DepartmentDSITDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£5.4bnDifference−£189m | | | | | |
| COLLECTIONS, PACKAGING AND REFORMS PROGRAMMEDetails | DEFRA | Amber (independent) | £5.2bn | £1.2bn | +£4.0bn |
| DepartmentDEFRADelivery confidenceAmber (independent)Whole-life cost, March 2025£1.2bnDifference+£4.0bn | | | | | |
| FUTURE BORDER AND IMMIGRATION SYSTEM PROGRAMME (FBIS)Details | HO | Amber (independent) | £5.1bn | £4.5bn | +£605m |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£4.5bnDifference+£605m | | | | | |
| MECHANISED INFANTRY PROGRAMMEDetails | MOD | Amber (independent) | £5.0bn | £7.0bn | −£2.0bn |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£7.0bnDifference−£2.0bn | | | | | |
| FLOOD AND COASTAL EROSION RISK MANAGEMENTDetails | DEFRA | Green (independent) | £4.8bn | £4.6bn | +£222m |
| DepartmentDEFRADelivery confidenceGreen (independent)Whole-life cost, March 2025£4.6bnDifference+£222m | | | | | |
| HOUSING INFRASTRUCTURE FUNDDetails | MHCLG | Amber (department’s own) | £4.3bn | £4.3bn | −£14m |
| DepartmentMHCLGDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£4.3bnDifference−£14m | | | | | |
| Flood and Coastal Risk Management (FCRM) Investment Programme 2026-2029Details | DEFRA | Amber (independent) | £3.9bn | Not in the portfolio | — |
| DepartmentDEFRADelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| PUBLIC SECTOR DECARBONISATION SCHEMEDetails | DESNZ | Amber (department’s own) | £3.8bn | £3.8bn | −£77m |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£3.8bnDifference−£77m | | | | | |
| MENSADetails | MOD | Amber (independent) | £3.6bn | £2.9bn | +£626m |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£2.9bnDifference+£626m | | | | | |
| Workplace TransformationDetails | DWP | Amber (independent) | £3.4bn | £3.5bn | −£140m |
| DepartmentDWPDelivery confidenceAmber (independent)Whole-life cost, March 2025£3.5bnDifference−£140m | | | | | |
| PFI Prison Expiry and Transfer Tranche 3Details | MOJ | Amber (department’s own) | £3.3bn | £4.6bn | −£1.3bn |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£4.6bnDifference−£1.3bn | | | | | |
| CLYDE INFRASTRUCTUREDetails | MOD | Amber (independent) | £3.3bn | Not published | — |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Boiler Upgrade SchemeDetails | DESNZ | Amber (department’s own) | £3.1bn | £794m | +£2.3bn |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£794mDifference+£2.3bn | | | | | |
| EAST COAST DIGITAL PROGRAMMEDetails | DFT | Red (independent) | £3.0bn | £3.5bn | −£435m |
| DepartmentDFTDelivery confidenceRed (independent)Whole-life cost, March 2025£3.5bnDifference−£435m | | | | | |
| Families First Partnership ProgrammeDetails | DFE | Amber (department’s own) | £2.9bn | Not in the portfolio | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| EUROPEAN COMMON RADAR SYSTEM MK 2Details | MOD | Amber (department’s own) | £2.9bn | £2.9bn | −£3m |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£2.9bnDifference−£3m | | | | | |
| BUILDING OUR FUTURE LOCATIONS PROGRAMMEDetails | HMRC | Green (department’s own) | £2.8bn | £2.9bn | −£52m |
| DepartmentHMRCDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£2.9bnDifference−£52m | | | | | |
| PFI Prison Expiry and Transfer Tranche 2Details | MOJ | Green (department’s own) | £2.7bn | £3.9bn | −£1.1bn |
| DepartmentMOJDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£3.9bnDifference−£1.1bn | | | | | |
| National Biosecurity Centre (Weybridge)Details | DEFRA | Green (independent) | £2.5bn | Not published | — |
| DepartmentDEFRADelivery confidenceGreen (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Hydrogen Allocation Round 1 (HAR1)Details | DESNZ | Amber (department’s own) | £2.5bn | £2.4bn | +£96m |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£2.4bnDifference+£96m | | | | | |
| SOCIAL HOUSING DECARBONISATION FUNDDetails | DESNZ | Amber (independent) | £2.3bn | £2.2bn | +£50m |
| DepartmentDESNZDelivery confidenceAmber (independent)Whole-life cost, March 2025£2.2bnDifference+£50m | | | | | |
| SUBMARINE WATERFRONT INFRASTRUCTURE FUTUREDetails | MOD | Red (independent) | £2.2bn | Not published | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| E7 WEDGETAILDetails | MOD | Red (department’s own) | £2.1bn | £2.0bn | +£165m |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025£2.0bnDifference+£165m | | | | | |
| COLLECTIVE TRAINING TRANSFORMATION PROGRAMMEDetails | MOD | Amber (independent) | £2.1bn | £2.1bn | −£23m |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£2.1bnDifference−£23m | | | | | |
| FRONTLINE DIGITISATIONDetails | DHSC | Amber (independent) | £2.1bn | £2.0bn | +£45m |
| DepartmentDHSCDelivery confidenceAmber (independent)Whole-life cost, March 2025£2.0bnDifference+£45m | | | | | |
| FE Capital TransformationDetails | DFE | Amber (department’s own) | £2.1bn | Not published | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| 2ND GENERATION UK SEARCH AND RESCUE AVIATIONDetails | DFT | Green (department’s own) | £2.0bn | £2.0bn | +£87m |
| DepartmentDFTDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£2.0bnDifference+£87m | | | | | |
| T-LevelsDetails | DFE | Amber (department’s own) | £2.0bn | £1.7bn | +£372m |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.7bnDifference+£372m | | | | | |
| MARSHALLDetails | MOD | Red (department’s own) | £2.0bn | £1.8bn | +£170m |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025£1.8bnDifference+£170m | | | | | |
| SYNERGY PROGRAMMEDetails | DWP | Amber (independent) | £2.0bn | £2.5bn | −£460m |
| DepartmentDWPDelivery confidenceAmber (independent)Whole-life cost, March 2025£2.5bnDifference−£460m | | | | | |
| Levelling Up Home Building FundDetails | MHCLG | Green (department’s own) | £2.0bn | £2.1bn | −£85m |
| DepartmentMHCLGDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£2.1bnDifference−£85m | | | | | |
| ARMOUR MBT 2025Details | MOD | Red (independent) | £2.0bn | £1.9bn | +£63m |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025£1.9bnDifference+£63m | | | | | |
| CHINOOK CAPABILITY SUSTAINMENT PROGRAMME (CSP)Details | MOD | Amber (department’s own) | £2.0bn | £1.9bn | +£46m |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.9bnDifference+£46m | | | | | |
| Drive 35Details | DBT | Green (department’s own) | £1.8bn | Not in the portfolio | — |
| DepartmentDBTDelivery confidenceGreen (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| HOME OFFICE BIOMETRICS (HOB) PROGRAMMEDetails | HO | Amber (independent) | £1.8bn | £1.6bn | +£260m |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£1.6bnDifference+£260m | | | | | |
| Prisoner Education ServicesDetails | MOJ | Amber (department’s own) | £1.8bn | £1.9bn | −£116m |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.9bnDifference−£116m | | | | | |
| PROTECTORDetails | MOD | Red (department’s own) | £1.7bn | £1.5bn | +£210m |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025£1.5bnDifference+£210m | | | | | |
| NEW STYLE OF INFORMATION TECHNOLOGY DEPLOYEDDetails | MOD | Red (independent) | £1.6bn | £1.4bn | +£200m |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025£1.4bnDifference+£200m | | | | | |
| POST OFFICE - TRANSFORMATIONDetails | DBT | Amber (independent) | £1.6bn | Not published | — |
| DepartmentDBTDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Brownfield, Infrastructure & Land (BIL)Details | MHCLG | Green (department’s own) | £1.5bn | £1.5bn | +£9m |
| DepartmentMHCLGDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£1.5bnDifference+£9m | | | | | |
| LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR)Details | MOD | Amber (independent) | £1.5bn | £1.9bn | −£380m |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£1.9bnDifference−£380m | | | | | |
| MAKING TAX DIGITALDetails | HMRC | Amber (independent) | £1.5bn | £1.4bn | +£46m |
| DepartmentHMRCDelivery confidenceAmber (independent)Whole-life cost, March 2025£1.4bnDifference+£46m | | | | | |
| GROUND BASED AIR DEFENCE (GBAD)Details | MOD | Amber (independent) | £1.5bn | £3.0bn | −£1.5bn |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025£3.0bnDifference−£1.5bn | | | | | |
| SELLAFIELD PRODUCT AND RESIDUE STORE RETREATMENT PLANT PROJECTDetails | DESNZ | Amber (department’s own) | £1.4bn | £1.5bn | −£38m |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.5bnDifference−£38m | | | | | |
| NEW MEDIUM HELICOPTERDetails | MOD | Amber (department’s own) | £1.4bn | £1.2bn | +£183m |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.2bnDifference+£183m | | | | | |
| EAST COAST MAINLINE PROGRAMMEDetails | DFT | Red (department’s own) | £1.3bn | £1.0bn | +£236m |
| DepartmentDFTDelivery confidenceRed (department’s own)Whole-life cost, March 2025£1.0bnDifference+£236m | | | | | |
| NATURE FOR CLIMATE FUNDDetails | DEFRA | Amber (independent) | £1.3bn | £928m | +£344m |
| DepartmentDEFRADelivery confidenceAmber (independent)Whole-life cost, March 2025£928mDifference+£344m | | | | | |
| Met Office Supercomputer ProgrammeDetails | DSIT | Amber (department’s own) | £1.2bn | £1.2bn | −£38m |
| DepartmentDSITDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.2bnDifference−£38m | | | | | |
| Electronic Monitoring ExpansionDetails | MOJ | Amber (independent) | £1.2bn | £858m | +£303m |
| DepartmentMOJDelivery confidenceAmber (independent)Whole-life cost, March 2025£858mDifference+£303m | | | | | |
| SERVICE MODERNISATION PROGRAMMEDetails | DWP | Amber (independent) | £1.1bn | £764m | +£386m |
| DepartmentDWPDelivery confidenceAmber (independent)Whole-life cost, March 2025£764mDifference+£386m | | | | | |
| SIXEP CONTINUITY PLANTDetails | DESNZ | Green (department’s own) | £1.1bn | £1.1bn | +£5m |
| DepartmentDESNZDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£1.1bnDifference+£5m | | | | | |
| Connect to WorkDetails | DWP | Green (independent) | £1.1bn | £1.4bn | −£279m |
| DepartmentDWPDelivery confidenceGreen (independent)Whole-life cost, March 2025£1.4bnDifference−£279m | | | | | |
| Law Enforcement Data ServiceDetails | HO | Amber (independent) | £1.1bn | £905m | +£182m |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£905mDifference+£182m | | | | | |
| FEDERATED DATA PLATFORMDetails | DHSC | Green (department’s own) | £1.1bn | £1.0bn | +£42m |
| DepartmentDHSCDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£1.0bnDifference+£42m | | | | | |
| Manchester Digital CampusDetails | CO | Amber (independent) | £1.0bn | £1.4bn | −£414m |
| DepartmentCODelivery confidenceAmber (independent)Whole-life cost, March 2025£1.4bnDifference−£414m | | | | | |
| Community Support ProgrammeDetails | MOJ | Amber (department’s own) | £1.0bn | Not in the portfolio | — |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| MIDLANDS RAIL HUBDetails | DFT | Amber (department’s own) | £948m | £1.6bn | −£621m |
| DepartmentDFTDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£1.6bnDifference−£621m | | | | | |
| MATRIX CLUSTER TRANSFORMATION PROGRAMMEDetails | DSIT | Red (department’s own) | £890m | £938m | −£48m |
| DepartmentDSITDelivery confidenceRed (department’s own)Whole-life cost, March 2025£938mDifference−£48m | | | | | |
| NO2 PROGRAMMEDetails | DEFRA | Amber (department’s own) | £843m | £883m | −£40m |
| DepartmentDEFRADelivery confidenceAmber (department’s own)Whole-life cost, March 2025£883mDifference−£40m | | | | | |
| EU Delivery ProgrammeDetails | DEFRA | Amber (independent) | £832m | Not in the portfolio | — |
| DepartmentDEFRADelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| Skills BootcampsDetails | DWP | Amber (department’s own) | £790m | £786m | +£5m |
| DepartmentDWPDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£786mDifference+£5m | | | | | |
| Health Transformation ProgrammeDetails | DWP | Amber (independent) | £735m | £3.0bn | −£2.3bn |
| DepartmentDWPDelivery confidenceAmber (independent)Whole-life cost, March 2025£3.0bnDifference−£2.3bn | | | | | |
| GREEN HEAT NETWORK FUNDDetails | DESNZ | Green (department’s own) | £730m | £702m | +£28m |
| DepartmentDESNZDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£702mDifference+£28m | | | | | |
| BEPPS2Details | DESNZ | Amber (department’s own) | £728m | £747m | −£20m |
| DepartmentDESNZDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£747mDifference−£20m | | | | | |
| HMRC NORTHERN IRELAND DELIVERY PROGRAMMEDetails | HMRC | Amber (department’s own) | £713m | £573m | +£140m |
| DepartmentHMRCDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£573mDifference+£140m | | | | | |
| GOV.UK One LoginDetails | DSIT | Amber (independent) | £709m | £342m | +£367m |
| DepartmentDSITDelivery confidenceAmber (independent)Whole-life cost, March 2025£342mDifference+£367m | | | | | |
| AUTOMOTIVE TRANSFORMATION FUND (ATF)Details | DBT | Green (department’s own) | £703m | £671m | +£32m |
| DepartmentDBTDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£671mDifference+£32m | | | | | |
| Children's Homes Capital ProgrammeDetails | DFE | Amber (department’s own) | £610m | Not in the portfolio | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| Contact Centre as a Service (CCaaS)Details | HMRC | Amber (independent) | £572m | Not in the portfolio | — |
| DepartmentHMRCDelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| A417 AIR BALLOONDetails | DFT | Green (department’s own) | £543m | £535m | +£8m |
| DepartmentDFTDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£535mDifference+£8m | | | | | |
| SUBMARINE DISMANTLING PROJECTDetails | MOD | Red (department’s own) | £542m | £400m | +£141m |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025£400mDifference+£141m | | | | | |
| Livestock Information Transformation ProgrammeDetails | DEFRA | Red (independent) | £526m | £478m | +£47m |
| DepartmentDEFRADelivery confidenceRed (independent)Whole-life cost, March 2025£478mDifference+£47m | | | | | |
| EURO 2028Details | DCMS | Amber (independent) | £512m | Not published | — |
| DepartmentDCMSDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| ENTERPRISE TAX MANAGEMENT PLATFORM (ETMP)Details | HMRC | Amber (department’s own) | £481m | £444m | +£37m |
| DepartmentHMRCDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£444mDifference+£37m | | | | | |
| Warm Homes: Local GrantDetails | DESNZ | Amber (independent) | £455m | Not published | — |
| DepartmentDESNZDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| NORTHERN IRELANDDetails | DEFRA | Green (department’s own) | £431m | £544m | −£114m |
| DepartmentDEFRADelivery confidenceGreen (department’s own)Whole-life cost, March 2025£544mDifference−£114m | | | | | |
| ASYLUM TRANSFORMATION PROGRAMMEDetails | HO | Amber (independent) | £430m | £362m | +£68m |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£362mDifference+£68m | | | | | |
| NATIONAL STRATEGIC AUTOMATIC NUMBER PLATE RECOGNITION PLATFORM (NSAP)Details | HO | Amber (department’s own) | £392m | £539m | −£147m |
| DepartmentHODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£539mDifference−£147m | | | | | |
| FreeportsDetails | MHCLG | Amber (department’s own) | £378m | £256m | +£122m |
| DepartmentMHCLGDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£256mDifference+£122m | | | | | |
| School-based nurseriesDetails | DFE | Amber (department’s own) | £370m | Not in the portfolio | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| ANTI-MONEY LAUNDERING AND ASSET RECOVERY (AMLAR)Details | HO | Amber (department’s own) | £368m | £414m | −£46m |
| DepartmentHODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£414mDifference−£46m | | | | | |
| Youth Investment FundDetails | DCMS | Amber (department’s own) | £360m | £310m | +£50m |
| DepartmentDCMSDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£310mDifference+£50m | | | | | |
| LOCAL LAND CHARGES (LLC) PROGRAMMEDetails | HMLR | Amber (department’s own) | £346m | £331m | +£15m |
| DepartmentHMLRDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£331mDifference+£15m | | | | | |
| Shared Rural NetworkDetails | DSIT | Green (department’s own) | £328m | £512m | −£184m |
| DepartmentDSITDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£512mDifference−£184m | | | | | |
| Civil Registration Service Transformation (CReST)Details | HO | Amber (department’s own) | £327m | £236m | +£91m |
| DepartmentHODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£236mDifference+£91m | | | | | |
| TERRESTRIAL NATURAL CAPITAL ECOSYSTEM ASSESSMENTDetails | DEFRA | Amber (department’s own) | £326m | Not published | — |
| DepartmentDEFRADelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| MODNET EVOLVEDetails | MOD | Green (independent) | £309m | £371m | −£61m |
| DepartmentMODDelivery confidenceGreen (independent)Whole-life cost, March 2025£371mDifference−£61m | | | | | |
| VOA NextGen Rating ProgrammeDetails | VOA | Amber (independent) | £300m | £329m | −£28m |
| DepartmentVOADelivery confidenceAmber (independent)Whole-life cost, March 2025£329mDifference−£28m | | | | | |
| CerberusDetails | HO | Amber (department’s own) | £285m | £241m | +£44m |
| DepartmentHODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£241mDifference+£44m | | | | | |
| Police National Database (PND)Details | HO | Amber (independent) | £283m | £388m | −£105m |
| DepartmentHODelivery confidenceAmber (independent)Whole-life cost, March 2025£388mDifference−£105m | | | | | |
| Warm Homes AgencyDetails | DESNZ | Red (independent) | £277m | Not in the portfolio | — |
| DepartmentDESNZDelivery confidenceRed (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| Decommission and Legacy Risk Migration (DLRM)Details | MOJ | Amber (department’s own) | £273m | £273m | −£0m |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£273mDifference−£0m | | | | | |
| Secure Children's Homes CommissioningDetails | MOJ | Green (department’s own) | £271m | £246m | +£25m |
| DepartmentMOJDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£246mDifference+£25m | | | | | |
| Enterprise Customer Relationship Management (eCRM)Details | HMRC | Amber (independent) | £257m | Not in the portfolio | — |
| DepartmentHMRCDelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| Evolve: WAN/LAN (Networks)Details | MOJ | Green (department’s own) | £254m | £253m | +£1m |
| DepartmentMOJDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£253mDifference+£1m | | | | | |
| UNITY PROGRAMMEDetails | HMRC | Red (independent) | £246m | £259m | −£13m |
| DepartmentHMRCDelivery confidenceRed (independent)Whole-life cost, March 2025£259mDifference−£13m | | | | | |
| DIGITAL PLANNING PROGRAMMEDetails | MHCLG | Amber (independent) | £219m | £148m | +£70m |
| DepartmentMHCLGDelivery confidenceAmber (independent)Whole-life cost, March 2025£148mDifference+£70m | | | | | |
| Natural History Museum UnlockedDetails | DCMS | Amber (department’s own) | £213m | £221m | −£8m |
| DepartmentDCMSDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£221mDifference−£8m | | | | | |
| ARMED FORCES RECRUITING PROGRAMMEDetails | MOD | Amber (department’s own) | £201m | Not published | — |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Evolve: End User Computer Service (EUCS)Details | MOJ | Green (department’s own) | £190m | £193m | −£3m |
| DepartmentMOJDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£193mDifference−£3m | | | | | |
| ConcordisDetails | NCA | Amber (department’s own) | £190m | Not in the portfolio | — |
| DepartmentNCADelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| INTEGRATED SINGLE FINANCIAL ENVIRONMENTDetails | DHSC | Green (independent) | £188m | £209m | −£21m |
| DepartmentDHSCDelivery confidenceGreen (independent)Whole-life cost, March 2025£209mDifference−£21m | | | | | |
| Evolve: Voice & VideoDetails | MOJ | Green (department’s own) | £185m | £385m | −£201m |
| DepartmentMOJDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£385mDifference−£201m | | | | | |
| British Museum - Energy Centre Programme (ECP)Details | DCMS | Green (department’s own) | £182m | £209m | −£27m |
| DepartmentDCMSDelivery confidenceGreen (department’s own)Whole-life cost, March 2025£209mDifference−£27m | | | | | |
| 4th National Lottery LicenceDetails | DCMS | Amber (independent) | £174m | £155m | +£20m |
| DepartmentDCMSDelivery confidenceAmber (independent)Whole-life cost, March 2025£155mDifference+£20m | | | | | |
| FRAUD AND CYBER CRIME REPORTING AND ANALYSIS SERVICEDetails | HO | Green (department’s own) | £169m | £183m | −£14m |
| DepartmentHODelivery confidenceGreen (department’s own)Whole-life cost, March 2025£183mDifference−£14m | | | | | |
| Cefas Infrastructure to Support Future Delivery at SeaDetails | DEFRA | Amber (department’s own) | £153m | Not published | — |
| DepartmentDEFRADelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Residential Property TribunalDetails | MOJ | Amber (department’s own) | £150m | Not in the portfolio | — |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| UK HOLOCAUST MEMORIAL AND LEARNING CENTREDetails | MHCLG | Red (department’s own) | £142m | £143m | −£1m |
| DepartmentMHCLGDelivery confidenceRed (department’s own)Whole-life cost, March 2025£143mDifference−£1m | | | | | |
| TOKYO NEW BUILD, REMODELLING AND REFURBISHMENTDetails | FCDO | Amber (department’s own) | £111m | £101m | +£10m |
| DepartmentFCDODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£101mDifference+£10m | | | | | |
| NHS Digital Transformation of ScreeningDetails | DHSC | Amber (department’s own) | £95m | £107m | −£12m |
| DepartmentDHSCDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£107mDifference−£12m | | | | | |
| PUBLIC OWNERSHIP TRANSITION PROGRAMMEDetails | DFT | Amber (independent) | £37m | £37m | +£0m |
| DepartmentDFTDelivery confidenceAmber (independent)Whole-life cost, March 2025£37mDifference+£0m | | | | | |
| Transforming Public ProcurementDetails | CO | Green (department’s own) | £32m | £32m | +£1m |
| DepartmentCODelivery confidenceGreen (department’s own)Whole-life cost, March 2025£32mDifference+£1m | | | | | |
| Review of Electricity Market Arrangements (REMA)Details | DESNZ | Green (department’s own) | £29m | Not published | — |
| DepartmentDESNZDelivery confidenceGreen (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Falcon ProgrammeDetails | CO | Amber (department’s own) | £23m | £24m | −£1m |
| DepartmentCODelivery confidenceAmber (department’s own)Whole-life cost, March 2025£24mDifference−£1m | | | | | |
| Future Service ProgrammeDetails | CO | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | £239m | — |
| DepartmentCODelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025£239mDifference— | | | | | |
| Strategic Sites Accelerator (SSA)Details | DBT | Amber (independent) | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not in the portfolio | — |
| DepartmentDBTDelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| HyNet ClusterDetails | DESNZ | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDESNZDelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| Great British EnergyDetails | DESNZ | Amber (independent) | Exempt under Section 22 - Information intended for future publication | Not in the portfolio | — |
| DepartmentDESNZDelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| GBE-N SMR ProgrammeDetails | DESNZ | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDESNZDelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| GEOLOGICAL DISPOSAL FACILITYDetails | DESNZ | Red (independent) | Low: 20,300.00, Mid: 26,350.29, High: 53,300.00 | Not published | — |
| DepartmentDESNZDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Sizewell C ProjectDetails | DESNZ | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDESNZDelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| East Coast Cluster (ECC)Details | DESNZ | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDESNZDelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| Spherical Tokamak for Energy ProductionDetails | DESNZ | Amber (independent) | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not published | — |
| DepartmentDESNZDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| School Rebuilding ProgrammeDetails | DFE | Amber (department’s own) | Exempt under Section 22 - Information intended for future publication | Not published | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Free Breakfast ClubsDetails | DFE | Exempt under Section 35 - Formulation of government policy | Exempt under Section 35 - Formulation of government policy | Not in the portfolio | — |
| DepartmentDFEDelivery confidenceExempt under Section 35 - Formulation of government policyWhole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| Lifelong Learning EntitlementDetails | DFE | Amber (department’s own) | Exempt under Section 22 - Information intended for future publication | Not published | — |
| DepartmentDFEDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| HS2 PHASE IDetails | DFT | Red (independent) | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not published | — |
| DepartmentDFTDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| EAST WEST RAIL CONNECTION STATE 1Details | DFT | Exempt under Section 43 - Commercial interests, Section 35 - Formulation of government policy | Exempt under Section 43 - Commercial interests, Section 35 - Formulation of government policy | £1.4bn | — |
| DepartmentDFTDelivery confidenceExempt under Section 43 - Commercial interests, Section 35 - Formulation of government policyWhole-life cost, March 2025£1.4bnDifference— | | | | | |
| REDEVELOPMENT EUSTON CONVENTIONAL STATION (RECS)Details | DFT | Exempt under Section 35 - Formulation of government policy | Exempt under Section 35 - Formulation of government policy | Not published | — |
| DepartmentDFTDelivery confidenceExempt under Section 35 - Formulation of government policyWhole-life cost, March 2025Not publishedDifference— | | | | | |
| A428 BLACK CAT TO CAXTON GIBBETDetails | DFT | Green (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDFTDelivery confidenceGreen (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Rail Reform: Stand-Up of GBRDetails | DFT | Red (independent) | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not in the portfolio | — |
| DepartmentDFTDelivery confidenceRed (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| A66 Northern Trans-PennineDetails | DFT | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDFTDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| EAST WEST RAIL CONNECTION STATE 2 AND 3Details | DFT | Amber (department’s own) | Exempt under Section 35 - Formulation of government policy, Section 43 - Commercial interests | £4.0bn | — |
| DepartmentDFTDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£4.0bnDifference— | | | | | |
| UK Health Security CampusDetails | DHSC | Exempt under Section 35 - Formulation of government policy | Exempt under Section 35 - Formulation of government policy | Not published | — |
| DepartmentDHSCDelivery confidenceExempt under Section 35 - Formulation of government policyWhole-life cost, March 2025Not publishedDifference— | | | | | |
| Future NHS Workforce Solution Transformation ProgrammeDetails | DHSC | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDHSCDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| MODERNA STRATEGIC PARTNERSHIP PROGRAMMEDetails | DHSC | Exempt under Section 43 - Commercial interests | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDHSCDelivery confidenceExempt under Section 43 - Commercial interestsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| PENSIONS DASHBOARD PROGRAMMEDetails | DWP | Amber (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentDWPDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| NS&I TransformationDetails | HMT | Red (independent) | Exempt under Section 43 - Commercial interests | £3.0bn | — |
| DepartmentHMTDelivery confidenceRed (independent)Whole-life cost, March 2025£3.0bnDifference— | | | | | |
| MARITIME CAPABILITIES REPLACEMENT PROGRAMMEDetails | HO | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/… | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not published | — |
| DepartmentHODelivery confidenceThe GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/…Whole-life cost, March 2025Not publishedDifference— | | | | | |
| RADIOLOGICAL AND NUCLEAR CHANGE PROGRAMME (RNCP)Details | HO | Exempt under Section 24 - National security | Exempt under Section 24 - National security | Not published | — |
| DepartmentHODelivery confidenceExempt under Section 24 - National securityWhole-life cost, March 2025Not publishedDifference— | | | | | |
| Asylum Support Accommodation ProgrammeDetails | HO | Red (independent) | Exempt under Section 43 - Commercial interests | £72.1bn | — |
| DepartmentHODelivery confidenceRed (independent)Whole-life cost, March 2025£72.1bnDifference— | | | | | |
| Immigration Removal Centre (IRC) Expansion ProgrammeDetails | HO | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentHODelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| ASYLUM ACCOMMODATION PROGRAMME (AAP)Details | HO | Red (independent) | Exempt under Section 43 - Commercial interests | £2.5bn | — |
| DepartmentHODelivery confidenceRed (independent)Whole-life cost, March 2025£2.5bnDifference— | | | | | |
| GRENFELL SITE AND PROGRAMMEDetails | MHCLG | Amber (department’s own) | The GMPP project is still at the planning stage (Pre-SOC or equivalent) and is not yet in a position to provide cost/sch | Not published | — |
| DepartmentMHCLGDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| FUTURE CRUISE ANTI SHIP WEAPON (FCASW)Details | MOD | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| MULTI ROLE STRIKE SHIPDetails | MOD | Red (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| FUTURE AIR DOMINANCE SYSTEMDetails | MOD | Red (independent) | Exempt under Section 43 - Commercial interests | Not in the portfolio | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| TYPE 26 GLOBAL COMBAT SHIP PROGRAMMEDetails | MOD | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| SKYNET 6 (AKA FBLOS)Details | MOD | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| DREADNOUGHTDetails | MOD | Exempt under Section 24 - National security | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceExempt under Section 24 - National securityWhole-life cost, March 2025Not publishedDifference— | | | | | |
| BRIMSTONE 3Details | MOD | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| TEUTATESDetails | MOD | Exempt under Section 27 - International relations | Exempt under Section 27 - International relations | Not published | — |
| DepartmentMODDelivery confidenceExempt under Section 27 - International relationsWhole-life cost, March 2025Not publishedDifference— | | | | | |
| SPEARFISH UPGRADE PROGRAMMEDetails | MOD | Exempt under Section 24 - National security | Exempt under Section 24 - National security | Not published | — |
| DepartmentMODDelivery confidenceExempt under Section 24 - National securityWhole-life cost, March 2025Not publishedDifference— | | | | | |
| NEXT GENERATION (FIXED) COMMUNICATION NETWORKDetails | MOD | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Future Materials CampusDetails | MOD | Exempt under Section 24 - National security | Exempt under Section 22 - Information intended for future publication | Not published | — |
| DepartmentMODDelivery confidenceExempt under Section 24 - National securityWhole-life cost, March 2025Not publishedDifference— | | | | | |
| SPEARCAP 3Details | MOD | Red (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| SUBMERSIBLE SHIP NUCLEAR AUKUSDetails | MOD | Amber (independent) | Exempt under Section 35 - Formulation of government policy | Not published | — |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Mobile Fires PlatformDetails | MOD | Amber (independent) | Exempt under Section 43 - Commercial interests | Not in the portfolio | — |
| DepartmentMODDelivery confidenceAmber (independent)Whole-life cost, March 2025Not in the portfolioDifference— | | | | | |
| FLEET SOLID SUPPORTDetails | MOD | Amber (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceAmber (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| LIGHTNING PROGRAMMEDetails | MOD | Green (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceGreen (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| MINE HUNTING CAPABILITYDetails | MOD | Red (department’s own) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (department’s own)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| FUTURE COMBAT AIR SYSTEMDetails | MOD | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| TYPE 31Details | MOD | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMODDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| JOINT CRYPT KEY PROGRAMMEDetails | MOD | Exempt under Section 23 - Information supplied by, or relating to, bodies dealing with security matters | Exempt under Section 23 - Information supplied by, or relating to, bodies dealing with security matters | Not published | — |
| DepartmentMODDelivery confidenceExempt under Section 23 - Information supplied by, or relating to, bodies dealing with security mattersWhole-life cost, March 2025Not publishedDifference— | | | | | |
| Small Secure HouseblocksDetails | MOJ | Amber (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| 10K Additional Prison Places Estate Expansion Houseblocks and RefurbishmentsDetails | MOJ | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Rapid Deployment Cells ProjectDetails | MOJ | Amber (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Property Transformation ProgrammeDetails | MOJ | Amber (department’s own) | Exempt under Section 43 - Commercial interests | £6.8bn | — |
| DepartmentMOJDelivery confidenceAmber (department’s own)Whole-life cost, March 2025£6.8bnDifference— | | | | | |
| 10k Additional Prison Places - New BuildDetails | MOJ | Amber (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| 10K Additional Prison Places Estate Expansion Category DDetails | MOJ | Red (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceRed (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |
| Accelerated HouseblocksDetails | MOJ | Amber (independent) | Exempt under Section 43 - Commercial interests | Not published | — |
| DepartmentMOJDelivery confidenceAmber (independent)Whole-life cost, March 2025Not publishedDifference— | | | | | |










Projects are matched to the year before by their portfolio ID. A difference in whole-life cost can come from a
change in scope, in timing or in how costs are counted as well as from overspending, and the two years’ figures may
be on different price bases (see above), so the difference is shown as published and not explained here. Each
department’s commentary on its projects is in the source file.



Source: [Infrastructure and Projects Authority, now the National Infrastructure and Service Transformation Authority, Government Major Projects Portfolio data](https://www.gov.uk/government/collections/major-projects-data), March 2022 to March 2026.





## What have auditors and MPs found?



The National Audit Office’s latest value-for-money reports and the Public Accounts Committee’s latest reports, each linked in full:



### National Audit Office


- 11 September 2026[Upgrading the electricity transmission network](https://www.nao.org.uk/reports/upgrading-the-electricity-transmission-network/) Value for money report
- 9 September 2026[Managing the flow of patients through hospital from A&E](https://www.nao.org.uk/reports/managing-the-flow-of-patients-through-hospital-from-ae/) Value for money report
- 4 September 2026[Resilience of the food supply chain to disruptions](https://www.nao.org.uk/reports/resilience-of-the-food-supply-chain-to-disruptions/) Value for money report
- 13 July 2026[Increasing construction skills](https://www.nao.org.uk/reports/increasing-construction-skills/) Value for money report
- 10 July 2026[Electronic monitoring: improving resilience to meet increasing demand](https://www.nao.org.uk/reports/electronic-monitoring-improving-resilience-to-meet-increasing-demand/) Value for money report
- 1 July 2026[Devolution in England: funding and accountability](https://www.nao.org.uk/reports/devolution-in-england-funding-and-accountability/) Value for money report
- 29 June 2026[High Speed Two reset](https://www.nao.org.uk/reports/high-speed-two-reset/) Value for money report
- 26 June 2026[The repurchase of the service family accommodation estate](https://www.nao.org.uk/reports/the-repurchase-of-the-service-family-accommodation-estate/) Value for money report




### Public Accounts Committee


- 18 September 2026[15th Report - Government's intervention in British Steel Ltd](https://committees.parliament.uk/publications/55075/) HC HC 101, 2026-27
- 11 September 2026[13th Report - Regulation of water, energy and broadband](https://committees.parliament.uk/publications/54964/) HC HC 105, 2026-27
- 9 September 2026[12th Report - Government compensation schemes](https://committees.parliament.uk/publications/54849/) HC HC 88, 2026-27
- 17 July 2026[11th Report - Unlocking land for housing](https://committees.parliament.uk/publications/54344/) HC HC 87, 2026-27
- 15 July 2026[10th Report - Government shared services](https://committees.parliament.uk/publications/54217/) HC HC 85, 2026-27
- 10 July 2026[9th Report - Large business tax compliance](https://committees.parliament.uk/publications/54140/) HC HC 86, 2026-27
- 1 July 2026[8th Report - Northern Powerhouse Rail](https://committees.parliament.uk/publications/53897/) HC HC 97, 2026-27
- 24 June 2026[7th Report - Financial resilience of government-sponsored museums and galleries](https://committees.parliament.uk/publications/53768/) HC HC 96, 2026-27

## Related pages

- [Next in this section: Fraud, error and write-offs](https://whereyourmoneygoes.co.uk/fraud-error-and-write-offs/)
- [Who does the government give its contracts to?](https://whereyourmoneygoes.co.uk/government-contracts/)
- [Where does my tax money actually go?](https://whereyourmoneygoes.co.uk/for-every-100-pounds-of-tax/)
- [How is each figure on this site worked out?](https://whereyourmoneygoes.co.uk/methodology/)

## More from this publisher

- [UK tax calculators](https://howlongisit.co.uk)

Published by [Tekstak Ltd](https://tek-stak.co.uk). Our words, analysis, charts and derived calculations: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/), credit [Tekstak Ltd](https://tek-stak.co.uk). The figures belong to the publishers listed under Sources and are used under their licences. Figures last updated 29 September 2026.